Tuesday, July 26, 2011

Duke Power


Duke Energy installed the power lines and transformer today. Hopefully they will have power hooked up to the temp pole tomorrow

Tuesday, July 12, 2011

Slab


The Slab is poured. The white dust you see on the slab is saw dust from the control joints in the slab.The slab was sealed prior to cutting so the dust will wash right off.

Monday, July 11, 2011

Slab

The concrete slab is being poured today. It is expected to be over 100 degrees today. With that in mind the concrete crew got started early today.

The ground is still really wet from all the rain last week. It is not supposed to rain today, but showers are likely for the rest of week.

After today Roger can finish the back fill and grade work on the driveway and around the house.

Friday, July 8, 2011

Slab Preperation


The foundation is being prepared for the slab work. We passed inspection today for the slab and temporary pole. Hopefully we will have electrical power on the temp pole next week. We are going to pour the slab on Monday morning. We have had a lot of down pours this week. The site is a little muddy right now.

Tuesday, July 5, 2011

Inspection

The rough plumbing passed inspection. Now we need to prep and form for the slab. Go forth is scheduled to come out and pre- treat the slab for termites.

Rough Plumbing

The lower level rough plumbing is complete and awaiting inspection

Under Slab Plumbing


Charlie Sims installing the under slab plumbing with the help of Roger Davis and his backhoe

Temporary Pole


Mac has installed the temporary pole. Jim needs to call Duke power and sent up the account for service.

Foundation waterproofing

Ronnie applying waterproofing agent

Waterproofing

Wall drain is being installed. A layer of "tar" was applied to the wall before the wall drain.