The windows and doors are installed and the finishing touches are being completed on the exterior siding. The porch / deck handrails are being installed. Next we plan to construct the retaining wall, drill the well and grade the site. After that the focus will shift to the inside, where the plumbers have already started.
Thursday, December 15, 2011
Wednesday, December 7, 2011
Tuesday, December 6, 2011
Friday, December 2, 2011
Siding Begins
We have selected LP smartsiding for the Hallmark Lodge.It is a phenomenal product. It comes in longer lengths than other products. It has a more defined wood profile. The warranty is much better. It has a 50/5 parts/labor warranty. In the gables we have installed a staggered edge shake. The walls are finished inch 6" lap siding.
Jonathan Nailed the View Angle
Rumbling Bald Mountain |
Wednesday, November 23, 2011
Happy Thanksgiving
Tuesday, November 15, 2011
Wednesday, November 9, 2011
Tuesday, November 8, 2011
Thursday, November 3, 2011
What a Difference Two Weeks Makes
The Family Room, Deck Columns and Lower Level Bedrooms |
The Front Entrance |
The View from the Family Room |
Its hard to believe that when I was on-site two weeks ago we were just setting the trusses. Now, the framing and sheathing on the front is essentially complete. On the back, the roof-line from the family room extends over the deck so the deck has to be completed first, but that should start in the next 1-2 days.
Tuesday, November 1, 2011
Friday, October 28, 2011
Thursday, October 27, 2011
Concrete Porch and Deck Footings
The Footings are dug for the deck and porch off of the rear of the house.
The First stage of prep for the front Porch
The Zip flashing is installed around all of the seems
The Final stage of Weathersheild is applied
The seems are taped and the fabric is ready
for the final prep work to be completed by
Mosseller Concrete.
The seems are taped and the fabric is ready
for the final prep work to be completed by
Mosseller Concrete.
Tuesday, October 25, 2011
Shaping up
Thursday, October 20, 2011
The Trusses are Set
Finally, it was a clear, cool (sometimes breezy) Autumn day, the crane was available, and the trusses were set by 1.00 PM. btw - there is a triangular cap that goes on top of each truss, the roof will really NOT be flat on the top.
Tuesday, October 18, 2011
Zip Wall
Sunday, October 9, 2011
Shaping Up
Standing in the Family Room |
The front of the house |
Wednesday, October 5, 2011
Friday, September 30, 2011
Subfloor
Wednesday, September 28, 2011
Tuesday, September 27, 2011
Wednesday, September 21, 2011
Friday, August 12, 2011
We Have Power
Both the electrical kind, from Duke - and the intellectual kind from the Team pictured below.
From the left: Jonathan, the general contractor; Roger, all the site excavation and driveway construction; Vince, the architect (from Asheville); and, Andy, a year-around neighbor and advisor.
From the left: Jonathan, the general contractor; Roger, all the site excavation and driveway construction; Vince, the architect (from Asheville); and, Andy, a year-around neighbor and advisor.
Tuesday, July 26, 2011
Duke Power
Tuesday, July 12, 2011
Slab
Monday, July 11, 2011
Slab
The concrete slab is being poured today. It is expected to be over 100 degrees today. With that in mind the concrete crew got started early today.
The ground is still really wet from all the rain last week. It is not supposed to rain today, but showers are likely for the rest of week.
After today Roger can finish the back fill and grade work on the driveway and around the house.
The ground is still really wet from all the rain last week. It is not supposed to rain today, but showers are likely for the rest of week.
After today Roger can finish the back fill and grade work on the driveway and around the house.
Subscribe to:
Posts (Atom)